DWE GmbH will supply the methanation technology for Nordic Ren-Gas Oy's e-methane plant in Tampere, Finland, after the project reached a final investment decision. The unit is designed for a plant with 50 MW of electrolysis capacity and will convert hydrogen from an electrolyzer and captured biogenic carbon dioxide into renewable e-methane.
Under the arrangement, DWE is responsible for the process license and design, prefabrication, manufacturing, testing, delivery, installation supervision, commissioning and performance testing of the methanation unit. The company said the unit will be delivered as prefabricated, factory-tested modules, an approach intended to shorten on-site construction and reduce interface risks.
Feedstock and output
The Tampere plant is expected to use around 40,000 metric tons of biogenic CO2 per year, captured from flue gases at the Tarastenjärvi waste-to-energy plant. It is expected to produce approximately 190 GWh of renewable e-methane annually for the European market, plus up to 200 GWh of district heat for Tampere. The e-methane is to be injected into the Finnish gas grid and supplied to end users in the German transport sector through the interconnected European gas network.
The project combines several elements of a power-to-gas chain: electrolysis to produce hydrogen, capture of biogenic CO2 from a waste-to-energy plant, catalytic methanation to produce e-methane, injection into the gas grid, and recovery of district heat. According to the announcement, the e-methane is intended for the European market, with German transport users named as end users connected through the European gas network. The district heat output is earmarked for Tampere.
Reactor design
DWE said its methanation technology was designed for renewable hydrogen from the outset. Christian Schuhbauer, head of new technologies at DWE, said the company's boiling-water-cooled tube bundle reactor performs the function of a cascade of adiabatic reactors without gas recycle or rotating equipment, and can follow renewable power loads from 30% to 100%. The description positions the unit for variable operation alongside electrolysis, although the announcement does not provide operating data from the Tampere plant.
Project partners and background
Christian Obermeier, head of PTX and technologies at DWE, described methanation as the heart of the power-to-gas value chain. He noted that DWE supplied the methanation unit for Europe's first commercial power-to-gas plant in Werlte, Germany, in 2012, and said the Tampere unit would turn renewable hydrogen and biogenic CO2 into high-quality e-methane. Martin Fraunhoffer, managing director of DWE, said the Ren-Gas Tampere project is DWE's first large-scale methanation project and fits its power-to-X strategy.
Saara Kujala, CEO of Nordic Ren-Gas, said the Tampere project brings together leading European technology partners to deliver renewable e-methane production at industrial scale. She described DWE's methanation technology and manufacturing capabilities as an important part of the value chain as the project moves into construction.