The Tees Valley combined authority has asked construction firms to advise on how a potential £1bn transport programme should be divided into packages, after submitting its five-year project list to the Department for Transport.
The programme is scheduled to run from April 2027 to March 2032 and covers major road schemes, railway upgrades, bus infrastructure, active travel and transport technology. The government has already confirmed £978m of core transport funding for the region, but the wider list goes beyond that sum and includes projects that still require further business case approvals and additional financial backing.
Inclusion on the wish-list therefore does not by itself confirm funding for any individual scheme.
Schemes named in the plan
Among the major road projects are the Darlington Northern Link Road and upgrades to the A66 and A689 corridors. Rail works include a new platform at Middlesbrough Station and the redevelopment of Thornaby Station.
The list also sets out ambitions for a new station at Teesside International Airport, improvements to Middlesbrough bus station and better transport links serving the Teesworks development.
The authority accepts that delivering the whole programme will hinge on government support and potentially further funding from outside sources.
Devolution does not close the funding gap
Steve Harker, the combined authority's cabinet member for transport and infrastructure, said it was important for people to understand that devolved status does not mean major transport schemes arrive fully funded. Government backing for the plans is vital, he said, because it would allow external bodies to help fund the programme and give the region the best chance of delivering as many projects as possible in good time.
Multiple contracts and an alliance option
Despite the funding uncertainty, the authority is pressing ahead with early supplier engagement to prepare its procurement strategy. It expects to let multiple contracts covering highways, rail, civil engineering and specialist infrastructure rather than award one giant deal.
It is also considering a programme-wide alliance built on the FAC-1 Framework Alliance Contract model, which would bring delivery partners together and is intended to encourage regional contractors and SMEs to participate.
Because the programme mixes road, rail and specialist infrastructure, splitting it into several contracts would spread the work across different disciplines and contract values.
Supplier feedback window
A supplier launch event was held on 9 November. Firms are now invited to give feedback through a market engagement questionnaire, with responses due by 1 March 2027. The exercise comes before the authority settles its procurement strategy.